1976
Project appears in Long Range Plan

1979
Original Public Hearing Held

1981
Final Environmental Impact Statement Circulated

1986
Concept of project revised to provide limited access right-of-way

1988
Public Meetings held

1992
Right-of-Way purchase begins south of 103rd Street

1995
Construction funded for two lane section

1997
Public Meetings held

2001
Planned roadway north of 103rd routed on former Cecil Field NAS property

2003
Public Hearing held for revised alignment north of 103rd Street

2005
Right-of-Way purchase begins north of 103rd Street

2009
Completed construction on section between Interstate 10 and Chaffee Road.

September 2012
Construction of frontage roads began on State Road 23 from Oakleaf Plantation Parkway to Old Jennings Road

September 2013
Construction of first phase of the First Coast Expressway began from I-10 to north of Argyle Forest Boulevard