First Coast Expressway

First Coast Expressway / Schedule

Schedule

FCE Segment 1 Est. Completion Date
FCE South Project
(Blanding Blvd to North of Argyle Blvd.)
Late 2017
FCE North Project
(North of Argyle Blvd. to I-10)
Late 2017
FCE Extension Project
(I-10 to Beaver Street/US 90)
Early 2018
FCE Segment 2 Est. Start Date Est. Completion Date
FCE North
(Blanding Blvd. in Middleburg to North of SR 16
in Green Cove Springs)
January 2019 2023
FCE South
(North of SR 16 to South of U.S. 17 by river
in Green Cove Springs)
January 2019 2023
FCE Segment 3 Status
New bridge over St. Johns River and
Connection to I-95 in St. Johns County
Right of Way acquisition estimated completion 2020; Design and Permitting estimated completion 2020

Construction not currently funded (outside of the 5-Year Work Plan)